Saturday, 14 September 2013

G324 - Rough Film Schedule

Location: Beach(9th November)
Crew will have to be there for sunrise. Actors will then arrive 1 hour after sunrise- 2 hours filming time.

Location: Park-Dogs and Picnic(5th November)
12-3pm

Location: Katies House-Fire Scene(13th November)
8pm-10pm

Location:Hayley's House-Christmas Scene(6th November)
3-5.30pm. Crew to arrive at 2pm to set up

Location: Katie's House-Resturant Scene(8th November)
7-9.30pm. Crew to arrive at 6 to set up.

Location: Drama Studio-Concert(15th November)
4.30-9. Crew to arrive at 3.30 to set up.

All of the dates for filming, apart from the concert, are subject to change due to the actors in our video having other commitments.

Editing will take place over several weeks, starting from the 18th November. This gives us plenty of time in case anything goes wrong and footage needs to be re-filmed.

We will use this schedule to make sure we complete all of our filming and editing on time. It shows us what needs to be filmed and when and if we fall behind on filming then we know we have a bit of spare time to complete any extra filming needed.

Posted by Abby

No comments:

Post a Comment